Context and the brief

For Kamal Enterprise’s GM Building Conference Hall project at Chittranjan Locomotive, West Bengal, IQUBX supplied and installed its WP01P partition system across approximately 3,000 sq. ft.

The project was completed in 2024, with Amrish Kumar Das serving as the architect/interior designer and Mr. Bapi, Kamal Enterprise as the PMC.

The installation was carried out directly at the site, with the focus on achieving a professional, refined partitioned space while avoiding unnecessary demolition and major civil work.

The site was live during installation, so the work had to proceed without disrupting other ongoing activity — with a wood-grain finish, no visible nails or fixings, and a structure the client could dismantle and relocate later without touching the existing building fabric.

Project at a glance

DetailsInformation
Client / End UserKamal Enterprise
LocationChittranjan, West Bengal
SectorGovernment
Building TypeGM Building Conference Hall
Architect / Interior DesignerAmrish Kumar Das
PMCMr. Bapi, Kamal Enterprise
IQUBX System InstalledWP01P
Panel MaterialPrelam Board
Panel Thickness12 mm
Area Installed3,000 sq. ft.
Completed2024
Installation Duration15–18 days
SupplyDirect

IQUBX Solution

Three priorities shaped the specification

Installation Without Demolition

The client required a new partition system without removing or damaging the existing walls or partitions. The solution therefore needed to minimize major civil work and avoid unnecessary disruption to the existing space.

 

Fast & Clean Installation

The project required a quick installation process with minimal site disturbance. The finished system needed to have no visible nails or exposed fixings, creating a neat and clean appearance appropriate for a professional conference-hall environment.

Professional Finish with Future Flexibility

The client wanted a modular partition solution that delivered a premium finished look while retaining the ability to dismantle, reconfigure or relocate the partitions as future space requirements changed.

The finished space

Placeholder photography — swap in real site images when available

Outcome

The Chittranjan Locomotive GM Building Conference Hall project was completed using the IQUBX WP01P partition system, covering approximately 3,000 sq. ft. with 12 mm prelam board panels.

The installation was completed in 15–18 days, with the solution designed around clean installation, minimal disruption, a professional finish and future flexibility through dismantling, reconfiguration and relocation.